- 8 August - Technical preview
- Major system components were updated, mass rebuilds were done after each major update.
- Iso package base is rebuilt with new dissuffix
- Customizing packages and theme are rebuilt
- Contrib preparation start
- Minimal guaranteed package base to be rebuilt is iso package base
- 22 August - Alpha
- Any not started features are declined
- Mass rebuilds are done
- 12 September - Beta0 ( internal )
- User Application freeze
- Image is released to approve application list.
- 3 October - Beta
- commit freeze ( minor part of people are still allowed to commit )
- 10 October - Hard freeze
- Hard freeze ( all commits are review by QA )
- final mass rebuild
- focus on cotrib
- localization freeze
- 24 October Beta2
- 14 November Release Candidate
- Possible release
- 28 November - релиз