Difference between revisions of "ROSA Desktop 2012 roadmap"
From Rosalab Wiki
Line 1: | Line 1: | ||
[[ru:ROSA_2012.1_ROADMAP]] | [[ru:ROSA_2012.1_ROADMAP]] | ||
− | * 8 August - Technical preview | + | * 8 August 2012 - Technical preview |
− | ** Major system | + | ** Major system update, mass rebuilds after each major update. |
− | ** Iso package base | + | ** Iso package base rebuild with new dissuffix |
− | ** Customizing packages and theme | + | ** Customizing packages and theme rebuilding |
− | ** Contrib preparation | + | ** Contrib preparation starts |
** Minimal guaranteed package base to be rebuilt is iso package base | ** Minimal guaranteed package base to be rebuilt is iso package base | ||
− | * 22 August - '''Alpha''' | + | * 22 August 2012 - '''Alpha''' |
** Any not started features are declined | ** Any not started features are declined | ||
** Mass rebuilds are done | ** Mass rebuilds are done | ||
− | * 12 September - Beta0 ( internal ) | + | * 12 September 2012 - Beta0 ( internal ) |
** User Application freeze | ** User Application freeze | ||
** Image is released to approve application list. | ** Image is released to approve application list. | ||
− | * 3 October - '''Beta''' | + | * 3 October 2012 - '''Beta''' |
** commit freeze ( minor part of people are still allowed to commit ) | ** commit freeze ( minor part of people are still allowed to commit ) | ||
− | * 10 October - Hard freeze | + | * 10 October 2012 - Hard freeze |
− | ** Hard freeze ( all commits are | + | ** Hard freeze ( all commits are reviewed by QA ) |
** final mass rebuild | ** final mass rebuild | ||
** focus on cotrib | ** focus on cotrib | ||
** localization freeze | ** localization freeze | ||
− | * 24 October '''Beta2''' | + | |
− | * 14 November '''Release Candidate''' | + | * 24 October 2012 '''Beta2''' |
− | ** Possible release | + | |
− | * 28 November - ''' | + | * 14 November 2012 '''Release Candidate''' |
+ | |||
+ | ** Possible release date | ||
+ | * 28 November 2012 - '''Release''' |
Revision as of 11:26, 16 June 2012
- 8 August 2012 - Technical preview
- Major system update, mass rebuilds after each major update.
- Iso package base rebuild with new dissuffix
- Customizing packages and theme rebuilding
- Contrib preparation starts
- Minimal guaranteed package base to be rebuilt is iso package base
- 22 August 2012 - Alpha
- Any not started features are declined
- Mass rebuilds are done
- 12 September 2012 - Beta0 ( internal )
- User Application freeze
- Image is released to approve application list.
- 3 October 2012 - Beta
- commit freeze ( minor part of people are still allowed to commit )
- 10 October 2012 - Hard freeze
- Hard freeze ( all commits are reviewed by QA )
- final mass rebuild
- focus on cotrib
- localization freeze
- 24 October 2012 Beta2
- 14 November 2012 Release Candidate
- Possible release date
- 28 November 2012 - Release