Difference between revisions of "ROSA Desktop 2012 roadmap"

From Rosalab Wiki
Jump to: navigation, search
Line 1: Line 1:
[[ROSA_2012.1_ROADMAP]]
+
[[ROSA 2012.1 ROADMAP]]
  
 
* 8 August - Technical preview
 
* 8 August - Technical preview

Revision as of 15:21, 15 June 2012

ROSA 2012.1 ROADMAP

  • 8 August - Technical preview
    • Major system components were updated, mass rebuilds were done after each major update.
    • Iso package base is rebuilt with new dissuffix
    • Customizing packages and theme are rebuilt
    • Contrib preparation start
    • Minimal guaranteed package base to be rebuilt is iso package base
  • 22 August - Alpha
    • Any not started features are declined
    • Mass rebuilds are done
  • 12 September - Beta0 ( internal )
    • User Application freeze
    • Image is released to approve application list.
  • 3 October - Beta
    • commit freeze ( minor part of people are still allowed to commit )
  • 10 October - Hard freeze
    • Hard freeze ( all commits are review by QA )
    • final mass rebuild
    • focus on cotrib
    • localization freeze
  • 24 October Beta2
  • 14 November Release Candidate
    • Possible release
  • 28 November - релиз