Difference between revisions of "ROSA Desktop 2012 roadmap"
From Rosalab Wiki
m |
m |
||
Line 21: | Line 21: | ||
** final mass rebuild | ** final mass rebuild | ||
− | * 24 October 2012 '''Beta''' | + | * 24 October 2012 - '''Beta''' |
** Hard freeze ( all commits are reviewed by QA ) | ** Hard freeze ( all commits are reviewed by QA ) | ||
**localization freeze | **localization freeze | ||
− | * 14 November 2012 '''Release Candidate''' | + | * 14 November 2012 - '''Release Candidate''' |
** Possible release date | ** Possible release date | ||
* 28 November 2012 - '''Release''' | * 28 November 2012 - '''Release''' |
Revision as of 07:35, 9 October 2012
- 8 August 2012 - Technical preview
- Major system update, mass rebuilds after each major update.
- Iso package base rebuild with new dissuffix
- Customizing packages and theme rebuilding
- Contrib preparation starts
- Minimal guaranteed package base to be rebuilt is iso package base
- 29 August 2012 - Alpha
- Any not started features are declined
- Mass rebuilds are done
- 9 October 2012 - Alpha2
- software versions freeze
- focus on cotrib
- 17 October 2012 - Internal control point
- commit freeze ( minor part of people are still allowed to commit )
- final mass rebuild
- 24 October 2012 - Beta
- Hard freeze ( all commits are reviewed by QA )
- localization freeze
- 14 November 2012 - Release Candidate
- Possible release date
- 28 November 2012 - Release